RCC framed structure with pile foundation confirming BIS requirements
Anti-termite treatment as per BIS requirements
All Walls with Solid blocks set in cement mortar
6″ thick solid blocks for the outer wall and 4″ thick solid blocks for all partitions
Wall Finish
Cement Plaster and JK/Birla putty finish with Premium Emulsion Paint for all internal Walls
External wall cement plaster finished with weather shield Max I Ace Exterior Emulsion
The Toilet will be finished with glazed ceramic tiles up to 7′ height
Toilet, Kitchen, Balconies, and other areas will be finished with cement plaster and emulsion
2 ft above the kitchen platform will be finished with glazed ceramic tiles
Floor Finishes
Living, Dining will be finished with 4’0″*2’0″ vitrified tiles with matching skirting and Bedroom & Kitchen will be finished with 2’*2′ vitrified tiles
Balconies and toilets will be finished with Non – slippery Ceramic Tiles
Wash I Service Area will be finished with non-slippery Ceramic Tiles
Ground Floor Lobbies and corridors will be finished with Granite
The staircase will be finished with vitrified tiles
Car park areas will be finished with Grano flooring
The driveway will be finished with interlocking blocks
Doors & Windows
Entrance Doors: Teakwood Frame with teak Veneered Flush Shutter. Godrej or Yale locks will be provided
Bedroom Doors: Teakwood frame and moulded skin panelled/ laminated doors. Godrej or Yale locks will be provided
Toilet Doors: Teakwood frame moulded skin panelled I laminated doors
Windows: UPVC window with MS Grill as per design of the architect
French Door: UPVC I Aluminium Sliding doors without grills
Ceiling
All ceiling areas will be finished with 2 coats of Putty with emulsion paint
Kitchen
2′ wide granite slab and a stainless steel bowl with drainboard sink would be provided
Provision for chimney and Aqua Guard will be made
Lift
The Building will be served with a 10 passenger lift of Johnson or Schindler
Toilets
White European Water closet of Kholer I Parryware will be provided in all toilets
All toilets will have provision for connecting a geyser
Health Faucet, diverter with an overhead shower will be provided in all toilets
All CP fittings will be of Jaquar/ Parryware
Electrical
Concealed insulated Copper Multi strand Finolex I Polycab Fire resistance wires in all apartments
Each Apartment will be provided with a distribution board having MCB’s
All switches & sockets of Legrand I Anchor
DG backup will be given for common facilities like pumps, lifts, STP, etc
Security
Provision will be given for intercom connection to the security
Provision will be given for CCTV cameras in the stilt lift lobbies, entry and exit gates
Common Toilet
Common Toilet for drivers and domestic help would be provided in the stilt floor
Compound wall
5 ft height compound wall on all the sides of the plot
sump
An underground sump of adequate capacity will be provided
Rainwater Harvesting
Will be provided as per the requirements of CMWSSB norms